關(guān)鍵詞:建筑電氣安裝;技術(shù)要求;質(zhì)量控制
Building electrical installation technical requirements and quality control
Liu Yuwen
Guangdong Province, Yangjiang 529500
Abstract: the construction of electrical installation construction is an important component of the project, has its special requirements and regulations, building electrical installation quality will directly affect the construction quality, and even endanger the production and people's life safety. The article analyses the construction of electrical installation technical requirements, discuss strengthen electrical installation engineering quality control strategy.
Key words: Construction of electrical installation; technical requirements; quality control
當(dāng)前,電氣安裝工程已成為高級(jí)建筑工程的重要組成部份,但電氣安裝工程質(zhì)量通病也是建筑施工中經(jīng)常發(fā)生并普遍存在的,由于量大面廣,因此對(duì)建筑工程質(zhì)量危害極大。在建筑工程中發(fā)生質(zhì)量事故究其原因是多方面的,除了施工人員在思想上對(duì)工程質(zhì)量重視不夠、施工企業(yè)管理不善外,主要在于近幾年來建筑隊(duì)伍迅速擴(kuò)大,技術(shù)力量相對(duì)薄弱,施工人員對(duì)如何清除工程質(zhì)量通病缺乏必要的理論知識(shí)和實(shí)踐經(jīng)驗(yàn),從而導(dǎo)致工程質(zhì)量問題經(jīng)常出現(xiàn),影響工程施工質(zhì)量。
1建筑電氣安裝的技術(shù)要求
1.在可燃結(jié)構(gòu)的天花頂棚內(nèi),不允許裝設(shè)電容器,電氣開關(guān)以及其他易燃易爆的用電器具。
2.在天花頂棚內(nèi)布線時(shí),應(yīng)在頂棚外設(shè)置電源開關(guān)。以便必要時(shí)切斷頂棚所有電氣線路的電源。
3.金屬線管適用范圍:除對(duì)金屬管有嚴(yán)重腐蝕者外,其他室內(nèi),外場所可采用金屬管布線。
4.潮濕場所以及埋地的金屬管布線,線管應(yīng)采用鍍鋅水管或煤氣鋼管。管壁厚度不應(yīng)小于0.5mm。
5.用金屬管保護(hù)的交流線路,應(yīng)將同一回路的各相導(dǎo)線穿在同―管內(nèi)。
6.管子所有連接點(diǎn)(包括接線盒,拉線盒,燈頭盒,開關(guān)盒等)均應(yīng)加跨接導(dǎo)線與管路焊接牢固。使管路成一電氣整體。其兩端問的電阻不應(yīng)大于l歐姆。跨接導(dǎo)線鍍鋅鐵線的最小截面應(yīng)不小于6mm。
7.金屬管配線,其點(diǎn)問的距離一般不應(yīng)大于以下尺寸:¢13~¢20管徑的管路,其間距為Im;¢25~¢32管徑的管路,其間距為1.5m;¢40~¢50管徑的管路,其間距為2m。
8.難燃管適用范圍:適用于室內(nèi)場所,對(duì)有酸堿腐蝕及潮濕場所尤其適用。
9.難燃管(槽)配線中的接線盒,拉線盒,開關(guān)盒等,應(yīng)采用難燃塑料盒,采用金屬盒代替。
10.管子布線的導(dǎo)線,可采用塑料線或穿管專用的膠麻線等絕緣導(dǎo)線。
11.穿管的導(dǎo)線總截面(包括外皮)應(yīng)不超過截面的40%。
12.同類照明的幾個(gè)回路,可以穿于同一管內(nèi),但管內(nèi)導(dǎo)線總數(shù)不應(yīng)多于8根。
13.管內(nèi)不允許有導(dǎo)線接頭,所有導(dǎo)線接頭應(yīng)裝設(shè)接線盒連接。
14.為保證鋼管配線和難燃管配線的穿線方便,下列情況應(yīng)裝拉線盒或放大管徑:
1)管子全長超過30m,且無彎曲或有一個(gè)彎曲時(shí);
2)管子全長超過20m,且有兩個(gè)彎曲時(shí);
3)管子全長超過10m,且有三個(gè)彎曲時(shí)。
15.敷設(shè)難燃型可撓管,超過下列長度時(shí)。其中問應(yīng)裝設(shè)分線盒或放大管徑:
1)管子全長超過20m,無彎曲時(shí);2)管子全長超過14m。只有一個(gè)彎曲時(shí);3)管子全長超過8M。有二個(gè)彎曲時(shí);4)管子全長超過5M,有三個(gè)彎曲時(shí)。
16.金屬管,難燃管配線的彎曲半徑,明敷時(shí)不得小于管子直徑的6倍。暗敷時(shí)不得小于管子直徑的10倍。
17.管路通過伸縮縫或沉降縫時(shí),應(yīng)加補(bǔ)償裝置。
18.電氣管路與水管路接近或交叉敷設(shè)時(shí),電氣管路一般敷設(shè)在熱水管下面,相互間的凈距不應(yīng)小于0.2M。
19.難燃型可撓管的連接及入接線盒均應(yīng)采用專用接頭連接。可撓管不允許在高層建筑中作豎向電源引線配管。
20.層內(nèi)照明線路的用電設(shè)備(包括電燈、風(fēng)扇、插座等),每一分路一般不超過25具,總?cè)萘坎怀^3000W。
21.每一單相回路的負(fù)荷電流一般應(yīng)不超過15A,并宜采用雙極膠殼開關(guān)或自動(dòng)開關(guān)控制和保護(hù)。
22.照明開關(guān)應(yīng)采用拉繩開關(guān)或墻邊開關(guān),不得采用燈頭開關(guān)(符合安全要求的臺(tái)燈除外)拉繩開關(guān)距地面高度為2-3M,墻邊開關(guān)距地面高度二般為1.3―1.5M。
23.插座容量與用電負(fù)荷相適應(yīng),每一插座只允許接用一個(gè)電具,并應(yīng)有熔斷保護(hù)。1KW及以上的用電設(shè)備,其插座前應(yīng)加裝閘也開關(guān)控樹。
24.插座安裝高度一般為1.3一1.5M,如小于1.3M,導(dǎo)直敷時(shí)應(yīng)加防護(hù)板(管),但任何情況下,插座與地面距離不得小于0.15M。
25.交流電氣用具、管線的接地裝置,首先應(yīng)利用與大地有可靠連接的,沒有燃燒及爆炸危險(xiǎn)的各種金屬結(jié)構(gòu)管道和設(shè)備作為自然接地體(如給排水管、鋼筋混凝土建筑物的基礎(chǔ))接地電阻不宜超過4Ω。
26.禁止使用金屬軟管、保溫管的金屬網(wǎng)和低壓照明網(wǎng)路導(dǎo)線外表的鋁皮作接地線。
27.電表的安裝高度應(yīng)方便裝拆和抄表,并應(yīng)考慮安全一箱底部對(duì)地面的垂直一般為1.7一1.9m。
2加強(qiáng)電氣安裝工程質(zhì)量控制的幾點(diǎn)建議
影響電氣安裝工程質(zhì)量的因素除了施工工藝外,原材料的控制和交接試驗(yàn)也起著至關(guān)重要的作用。原材料進(jìn)場時(shí)除了檢查外觀合格證及規(guī)范要求的相關(guān)檢驗(yàn)報(bào)告外,還應(yīng)對(duì)照?qǐng)D紙審查其型號(hào)、規(guī)格、材質(zhì)、數(shù)量及制作是否符合規(guī)范要求,對(duì)有條件進(jìn)行實(shí)測(如燈具的絕緣電阻、芯線截面積及電線的絕緣層厚度等)及有懷疑的應(yīng)進(jìn)行檢測。要認(rèn)真完成規(guī)定的試驗(yàn):如接地、絕緣電阻測試、漏電保護(hù)裝置模擬動(dòng)作試驗(yàn)、通電試運(yùn)行、大型燈具的固定及懸吊裝置的過載實(shí)驗(yàn)、高壓電氣設(shè)備和布線系統(tǒng)及繼電保護(hù)系統(tǒng)的交接試驗(yàn)等。
施工過程是檢驗(yàn)工程質(zhì)量的重要環(huán)節(jié),完善質(zhì)量保證體系除了必須加強(qiáng)工序控制,實(shí)行自檢、互檢、交接檢測制度外,還應(yīng)認(rèn)真審查項(xiàng)目的合法性及各方主體的質(zhì)量行為,審批施工組織設(shè)計(jì)并參與圖紙會(huì)審,嚴(yán)格變更制度,避免走過場。實(shí)際工程中,往往有建筑施工單位未經(jīng)設(shè)計(jì)許可,擅改開關(guān)型號(hào)、導(dǎo)線截面、增加負(fù)荷等,這些改動(dòng)使系統(tǒng)的選擇性、可靠性降低,致使保護(hù)電氣不動(dòng)作或誤動(dòng)作,給用戶的安全使用留下隱患。
3結(jié)束語
建筑電氣安裝是建筑工程的重要組成部分,有其特殊的要求和規(guī)定,建筑電氣安裝的質(zhì)量將直接影響整個(gè)建筑的質(zhì)量,甚至危及生產(chǎn)和人民生命安全,建筑電氣安裝的質(zhì)量問題在建筑工程中也是十分常見的,我們應(yīng)該引起足夠的重視。
參考文獻(xiàn):
[1]何增平.建筑電氣設(shè)計(jì)存在的若干問題對(duì)工程質(zhì)量的影響[J].福建建設(shè)科技,2005,(2).
[2]古杜章.淺談民用建筑電氣安裝工程的缺陷與防治[J].科教文匯,2005,(2).
[關(guān)鍵詞]變壓器安裝;安裝前的準(zhǔn)備;安裝工藝;質(zhì)量控制要點(diǎn)
中圖分類號(hào):TD353.5 文獻(xiàn)標(biāo)識(shí)碼:A 文章編號(hào):1009-914X(2015)44-0237-01
1.變壓器安裝前的準(zhǔn)備
1.1 技術(shù)準(zhǔn)備
(1)熟悉圖紙資料,弄清設(shè)計(jì)圖的設(shè)計(jì)內(nèi)容,注意圖紙和產(chǎn)品技術(shù)資料提出的具體施工要求。
(2)考慮與主體工程和其他工程的配合問題,確定施工方法。
(3)技術(shù)交底。施工前要認(rèn)真聽取工程技術(shù)人員的技術(shù)交底,弄清技術(shù)要求、技術(shù)標(biāo)準(zhǔn)和施工方法。
(4)必須熟悉有關(guān)電力工程的技術(shù)規(guī)范。
1.2 設(shè)備及材料、機(jī)具準(zhǔn)備
(1)查驗(yàn)合格證和隨帶技術(shù)文件,變壓器應(yīng)有出廠試驗(yàn)記錄。
(2)型鋼:各種規(guī)格型鋼應(yīng)符合設(shè)計(jì)要求,并無明顯銹蝕。
(3)螺栓:除地腳螺栓及防震裝置螺栓外,均應(yīng)采用不銹鋼螺栓,并配相應(yīng)的不銹鋼平墊圈和彈簧墊。
(4)其他所需要的材料均應(yīng)符合設(shè)計(jì)要求,并有產(chǎn)品合格證。
(5)安裝變壓器使用到的機(jī)具、設(shè)備準(zhǔn)備就緒
1.3 作業(yè)條件準(zhǔn)備
(1)變壓器室內(nèi)、墻面、屋頂、地面工程等應(yīng)完畢,屋頂防水無滲漏,門窗及玻璃安裝完好,地坪抹光工作結(jié)束,室外場地平整,設(shè)備基礎(chǔ)按工藝配制圖施工完畢。
(2)預(yù)埋件、預(yù)留孔洞等均已清理并調(diào)整至符合設(shè)計(jì)要求。
(3)保護(hù)性網(wǎng)門,欄桿等安全設(shè)施齊全,通風(fēng)、消防設(shè)置安裝完畢。
(4)與電力變壓器安裝有關(guān)的建筑物、構(gòu)筑物的建筑工程質(zhì)量應(yīng)符合現(xiàn)行建筑工程施工及驗(yàn)收規(guī)范的規(guī)定。當(dāng)變壓器設(shè)備及輔助設(shè)備有特殊要求時(shí),應(yīng)符合其特定要求。
2.開箱清點(diǎn)及附件檢查
在清點(diǎn)附件時(shí),主要進(jìn)行下列外觀檢查:(1)本體內(nèi)氣體壓力應(yīng)為正壓,壓力在0.01~0.03MPa之間。(2)根據(jù)裝箱清單檢查所到設(shè)備及附件的技術(shù)文件是否齊全,檢查變壓器外表有無機(jī)械損傷、溫度計(jì)、導(dǎo)油管等預(yù)留孔是否齊全各種封蓋螺絲是否齊全緊固,對(duì)分散包裝運(yùn)輸?shù)母郊辞鍐沃鹨磺妩c(diǎn)。(3)套管應(yīng)無損傷、無裂紋、無滲漏油,散熱器、油泵、導(dǎo)油管等應(yīng)密封良好。(4)檢查沖擊記錄儀X、Y、Z三維均小于3g (根據(jù)合同要求,需要時(shí)才檢查此項(xiàng))。(5)絕緣檢查和判斷,電力變壓器絕緣檢查的內(nèi)容包括:油箱的密封檢查、抽樣化驗(yàn)和線圈絕緣測量,以判斷變壓器的絕緣狀況。(6)器身檢查,變壓器因長途運(yùn)輸和裝卸,受到振動(dòng)和沖擊,使得在油箱內(nèi)產(chǎn)生位移,個(gè)別緊固件可能松動(dòng)或脫落,穿心螺栓也常因絕緣損壞而接地。進(jìn)行器身檢查,這些問題可得到及時(shí)發(fā)現(xiàn)和處理。
3.變壓器型鋼基礎(chǔ)的安裝
(1)鋼金屬構(gòu)架的幾何尺寸、應(yīng)符合設(shè)計(jì)基礎(chǔ)配制圖的要求與規(guī)定,如設(shè)計(jì)對(duì)型鋼構(gòu)架高出地面無要求,施工時(shí)可將其頂部高出100mm。
(2)型鋼基礎(chǔ)構(gòu)架與接地扁鋼連接不宜少于二端點(diǎn),在基礎(chǔ)型鋼的兩端,用不小于40x4mm的扁鋼相焊接,焊接扁鋼時(shí),焊縫長度應(yīng)為扁鋼的二倍,焊接三個(gè)棱邊,焊完后去氧化皮,焊縫應(yīng)均勻牢靠,焊接處做防腐處理后再刷兩遍灰面漆。
4.變壓器就位安裝
4.1 變壓器器體就位
變壓器就位之前,在基礎(chǔ)及變壓器上標(biāo)出縱橫中心線,變壓器按標(biāo)識(shí)就位,變壓器就位時(shí)要保證變壓器中心線與基礎(chǔ)中心線一致。
4.2 變壓器安裝
變壓器附件安裝。變壓器的附件安裝主要包括套管安裝、冷卻裝置安裝、儲(chǔ)油柜安裝、氣體繼電器安裝、安全氣道及呼吸器的安裝、分接開關(guān)安裝和凈油器及溫度計(jì)的安裝等。在進(jìn)行附件安裝時(shí),都應(yīng)按照規(guī)定的程序進(jìn)行。待變壓器安裝共走全部結(jié)束后,應(yīng)根據(jù)有關(guān)規(guī)定進(jìn)行綜合判斷新變壓器是否需要干燥。變壓器的干燥方法較多,但各種干燥方法的基本特點(diǎn)是一致的,就是加熱升溫和排潮。變壓器加熱升溫的方法主要有:油箱鐵損法、短路法、零序電流法和熱油法。排潮的方法主要有真空法、通風(fēng)法和濾油法。變壓器安裝完畢,對(duì)現(xiàn)場進(jìn)行清理之后,地面用3-5MM橡膠墊層作為絕緣。
在變壓器安裝過程中,必須滿足以下三個(gè)方面的質(zhì)量要求:
(1)保持變壓器器身和其他絕緣部件不受潮氣侵入。
(2)變壓器各導(dǎo)電部分的連接可靠,接觸良好。
(3)變壓器各附件與油箱的連接部位密封良好,不滲漏油。
5.變壓器試運(yùn)行
5.1 變壓器試運(yùn)行應(yīng)具備的條件
變壓器安裝工作完畢。包括變壓器本體、冷卻裝置及所有的附件均無缺陷,且不滲油;輪子制動(dòng)裝置固定牢固;油漆完整,相包標(biāo)志正確,接地可靠;變壓器頂蓋上無任何遺留物。
事故排油設(shè)施完好,消防設(shè)施齊全。
高壓套管的接地小套管已接地;電壓抽取裝置不同時(shí),其抽出端子已接地;套管頂部結(jié)構(gòu)的密封良好。
電壓切換裝置的位置符合運(yùn)行要求,有載調(diào)壓切換裝置,操作動(dòng)作可靠,指示位置正確。
變壓器的相位及線圈的連接組別符合并列運(yùn)行的要求。
溫度計(jì)指示正確,定值符合要求。
冷卻裝置運(yùn)行正常,聯(lián)動(dòng)正確,水冷裝置的油壓應(yīng)大于水壓;強(qiáng)迫油循環(huán)的變壓器以已啟動(dòng)全部冷卻裝置,并進(jìn)行了長時(shí)間循環(huán),放完殘留空氣。
保護(hù)裝置整定值符合規(guī)定,操作及聯(lián)動(dòng)試驗(yàn)正確。
5.2 變壓器試運(yùn)行
帶電,變壓器第一次受電時(shí),一般有兩種方法:一是變壓器從零升壓至額定值;若沒有條件從零升時(shí),可直接合上高壓側(cè)開關(guān),對(duì)變壓器進(jìn)行全電壓沖擊合閘。變壓器第一次受電10min后,若無異常情況,接著對(duì)變壓器進(jìn)行5次全電壓沖擊合閘試驗(yàn),以驗(yàn)證勵(lì)磁涌流能否引起保護(hù)裝置的誤動(dòng)。變壓器首次受電和全電壓沖擊合閘時(shí),應(yīng)設(shè)專人監(jiān)視變壓器有無異常情況,如有異常情況,應(yīng)立即停電處理。
定相、定相的目的是要檢查變壓器各側(cè)的電壓相序與運(yùn)行系統(tǒng)的電壓相序是否一致,如果其相序不一致,則不允許并列運(yùn)行。
經(jīng)過上述工作后,如果一切情況正常,即可將變壓器并入電網(wǎng)運(yùn)行。
變壓器并入電網(wǎng)后,按照電網(wǎng)的供電情況,逐步增加負(fù)荷,當(dāng)達(dá)到滿負(fù)荷以后,連續(xù)運(yùn)行24H,觀測變壓器的溫升和無其他異常情況后,試運(yùn)工作結(jié)束。
6.質(zhì)量要求及質(zhì)量控制的關(guān)鍵點(diǎn)
(1)變壓器安裝前應(yīng)選擇晴朗天氣,嚴(yán)格控制器身與空氣接觸時(shí)間;
(2)抽取真空時(shí)殘壓應(yīng)越低越好,并符合設(shè)計(jì)或制造廠有關(guān)規(guī)定,抽真空的速率不應(yīng)過快。不能承受真空機(jī)械強(qiáng)度的部件應(yīng)可靠隔離;
(3)保護(hù)法蘭平面清潔度,清除油污、銹蝕、銹跡。通過的密封圈嚴(yán)禁再用;
(4)對(duì)絕緣油進(jìn)行全過程控制,在到貨、過濾、注油前、注油后等各環(huán)節(jié),均要對(duì)其進(jìn)行嚴(yán)格的取樣化驗(yàn),出具化驗(yàn)報(bào)告單,確保合格;
(5)進(jìn)行注油排氮時(shí),確保整個(gè)器芯均浸在變壓器油內(nèi),并靜止24h以上,以確保器芯不易受潮;
(6)在進(jìn)行器身檢查或內(nèi)部引線的連接時(shí),必須在晴天進(jìn)行,空氣相對(duì)濕度要小于75%,暴露在空氣中的時(shí)間不得超過16h;器身檢查完畢,要經(jīng)監(jiān)理、廠家、施工單位質(zhì)檢簽證認(rèn)可;
(7)器身檢查用的工具、材料逐一登記上帳,并安排專人負(fù)責(zé),工作結(jié)束后,逐一進(jìn)行核對(duì),應(yīng)無差錯(cuò);
(8)對(duì)變壓器內(nèi)部抽真空前,對(duì)應(yīng)抽真空的附件進(jìn)行全面檢查,確保無遺漏,蝶閥已打開;對(duì)不允許抽真空的附件采取正確的防護(hù)隔離措施;
(9)真空注油后,對(duì)所有的附件、對(duì)接口、焊縫進(jìn)行檢查,不得有滲漏油現(xiàn)象;
(10)嚴(yán)格按規(guī)程和廠家安裝說明書中的程序和要求對(duì)變壓器進(jìn)行安裝,嚴(yán)格按電氣設(shè)備交接試驗(yàn)規(guī)程、廠家說明書對(duì)變壓器進(jìn)行各項(xiàng)試驗(yàn)測試,出具檢測試驗(yàn)報(bào)告。
關(guān)鍵詞:電氣系統(tǒng);安裝技術(shù);質(zhì)量控制
Abstract: in the construction engineering projects, electrical system is one of the important component, which directly affect the safety operation of the whole building equipment and to use a function. This article mainly from the building electrical installation and technical requirements of quality control two, discusses the electrical engineering to ensure the construction quality.
Keywords: electric system; Installation technology; Quality control
中圖分類號(hào): V351.31文獻(xiàn)標(biāo)識(shí)碼:A 文章編號(hào):
1 引言
隨著建筑電氣智能化技術(shù)的迅速發(fā)展,建筑業(yè)發(fā)展迅速,但伴隨著各種各樣的建筑質(zhì)量問題,尤其是建筑電氣的質(zhì)量問題。建筑電氣工程師一門內(nèi)容繁多、技術(shù)復(fù)雜和更新較快的綜合應(yīng)用技術(shù)。電氣本身可以分為強(qiáng)電和弱電兩大類,涉及相關(guān)的技術(shù)標(biāo)準(zhǔn)、規(guī)范,與土建給排水、暖通等專業(yè)密切配合,有機(jī)地構(gòu)成了功能完善的建筑統(tǒng)一體。為了提高房屋建設(shè)的總體質(zhì)量,就必須保證建筑電氣工程的施工質(zhì)量。建筑電氣工程,對(duì)于一個(gè)建設(shè)工程的使用功能、竣工后運(yùn)行的安全可靠程度、投資效益的體現(xiàn)等,都有著舉足輕重的地位。所以,電氣工程師要抓住電氣特點(diǎn),結(jié)合實(shí)際工程,編制好電氣安裝實(shí)施細(xì)則,做好電氣安裝工作。
2 建筑電氣安裝的技術(shù)要求
2.1施工前準(zhǔn)備
建筑電氣安裝是一項(xiàng)系統(tǒng)性的工程,在施工前必須對(duì)電氣管理和施工人員加強(qiáng)質(zhì)量教育、思想教育,對(duì)其進(jìn)行培訓(xùn)、優(yōu)選施工人員,提高他們的素質(zhì),使他們樹立質(zhì)量第一,預(yù)防為主的思想;還要他們?cè)敿?xì)了解安裝施工工序,熟悉施工過程,以保證電氣安裝工程的質(zhì)量。
在建筑電氣安裝工程的設(shè)計(jì)階段,電氣設(shè)計(jì)人員要對(duì)整個(gè)建筑項(xiàng)目有詳細(xì)的了解,并針對(duì)設(shè)計(jì)工作提出相關(guān)的技術(shù)要求。例如,電氣設(shè)備和線路固定件的預(yù)埋設(shè)計(jì),需要在建筑電氣安裝施工圖設(shè)計(jì)中有明確的標(biāo)識(shí)。另外,電氣安裝人員和施工技術(shù)人員要審核安裝施工圖紙,掌握安裝施工方法,了解施工進(jìn)度,以及某些關(guān)鍵地方的連接,如梁柱、柱、地面、屋面之間的連接方式。最后,建筑電氣安裝施工中所使用的預(yù)埋件也需要在工程開始之前加工制作完成,保證電氣安裝工程的順利實(shí)施。
2.2配電設(shè)備安裝工藝
配電箱是接受電能和分配電能的表量,也是電力負(fù)荷在現(xiàn)場的直接控制器。要使工程中的動(dòng)力、照明以及弱電負(fù)荷能正常工作,配電箱的工作性能至關(guān)重要。配電箱安裝應(yīng)在土建地面施工完后進(jìn)行,墻柱上明裝箱也應(yīng)在土建施工完后進(jìn)行,而暗裝配電箱、接線箱應(yīng)在土建抹灰裝飾前,根據(jù)抹灰厚度進(jìn)行。
所有配電箱不打開箱門時(shí)的防護(hù)等級(jí)不小于IP40,打開箱門后的防護(hù)等級(jí)不小于IP20,箱體安裝,按實(shí)際現(xiàn)場情況采用上(下) 進(jìn)上(下) 出接線方式制作。
2.3 電纜敷設(shè)工藝
在電纜敷設(shè)之前,要仔細(xì)核對(duì)電纜的規(guī)格以及型號(hào)是否符合設(shè)計(jì)的要求,并認(rèn)真檢查電纜的質(zhì)量是否合格,還要對(duì)電纜進(jìn)行絕緣測驗(yàn)。在進(jìn)行電纜敷設(shè)時(shí),多個(gè) 電纜之間不能交叉敷設(shè),電纜之間應(yīng)有序排列并進(jìn)行固定,在埋設(shè)電纜線路和接頭處設(shè)置標(biāo)志牌。按照由上而下的順序配置高低壓電力電纜以及強(qiáng)電與弱電控制電纜,對(duì)于普通支架上的控制電纜,一般以一層為宜,不宣過多;在橋架上的電纜最多不能超過三層。另外,電纜接頭的制作要嚴(yán)格按照設(shè)計(jì)要求進(jìn)行,對(duì)制作人員有較高的要求,同時(shí)還要有較好的制作環(huán)境,應(yīng)當(dāng)避免在有塵土和污物的環(huán)境中制作,防止接頭被污染。電纜接頭的制作必須一次性完成,不能讓剝開的電纜接頭置于潮濕的環(huán)境中,以免受潮,影響質(zhì)量。要注意,不能損壞電纜的芯線和絕緣,并且在進(jìn)行密封處理時(shí),要進(jìn)行防塵防潮處理,然后再進(jìn)行密封工作。電纜的接頭和終端頭以及絕緣層都應(yīng)進(jìn)行接地處理,一般采用銅絞線作為接地線,保障電纜的安全運(yùn)行。
2.4 開關(guān)、插座的安裝施工工藝
開關(guān)、插座、吊扇鉤盒等預(yù)埋時(shí),需要符合相關(guān)的圖紙要求,在施工定位時(shí),應(yīng)嚴(yán)格按照施工的基本要求:盒位前后、左右允許的偏差不大于50mm;同一室內(nèi)整排布置的燈具以及吊扇中心允許的偏差不大于5mm;開關(guān)盒距離門框一般為150―200mm。同一場所的開關(guān)分合方向要一致。連接插座時(shí)要注意單相兩、三孔插座“左零右火,上接地”的接線方式;單相三孔及三相四、五孔插座的上孔與PE線相連。潮濕場所要采用密封型且?guī)ПWo(hù)地線觸頭的插座,安裝高度不能低于1.5m。
3建筑電氣安裝質(zhì)量控制
(1)在電氣安裝施工中,要根據(jù)已經(jīng)會(huì)審后的電氣設(shè)計(jì)安裝圖紙和相關(guān)的技術(shù)文件,并按照國家現(xiàn)行的電氣工程安裝施工及驗(yàn)收的規(guī)范、地方有關(guān)工程建設(shè)的相關(guān)法規(guī)文件等,經(jīng)過相關(guān)審批的施工組織設(shè)計(jì)相關(guān)文件、圖紙進(jìn)行施工。
(2)對(duì)于電氣工程安裝施工中比較常見的質(zhì)量事故,要事先采取對(duì)策并加以控制,因此,要求電氣安裝人員對(duì)電氣安裝工程施工的全過程加以充分的研究,施工過程是質(zhì)量管理的主要環(huán)節(jié),根據(jù)已經(jīng)經(jīng)過會(huì)審的圖紙,按圖施工。施工過程中,注意每道工序都要按規(guī)范操作,并進(jìn)行檢驗(yàn),不得留下質(zhì)量隱患問題。
(3)工程所需的材料、器件和設(shè)備的質(zhì)量是保證工程質(zhì)量的主要因素,管理人員要對(duì)進(jìn)場的材料和設(shè)備進(jìn)行檢查,合格后方可進(jìn)入現(xiàn)場,并及時(shí)填寫“工程材料報(bào)驗(yàn)單”以及附加材料清單、材質(zhì)證明等。
(4)在施工現(xiàn)場,結(jié)合電氣工程施工的實(shí)際施工情況,組織施工人員學(xué)習(xí)施工驗(yàn)收規(guī)范、操作以及質(zhì)量標(biāo)準(zhǔn),使他們達(dá)到熟練掌握施工要求和質(zhì)量標(biāo)準(zhǔn)的目的。整個(gè)項(xiàng)目工程由許多分部分項(xiàng)工程組成,只有保證了每個(gè)分部分項(xiàng)工程的質(zhì)量,才能創(chuàng)造出優(yōu)良的項(xiàng)目工程。電氣工程質(zhì)量管理人員要與施工人員密切配合、共同努力,以保證電氣工程的質(zhì)量。
4 結(jié)論
隨著建筑技術(shù)的發(fā)展,建筑物的服務(wù)功能不斷增加、擴(kuò)大,建筑電氣化、自動(dòng)化、智能化的標(biāo)準(zhǔn)也不斷提高,對(duì)電氣系統(tǒng)的施工技術(shù)及質(zhì)量要求也越來越高。要想把電氣工程做好,電氣工程師應(yīng)把“質(zhì)量第一、安全第一”放在第首位。實(shí)際施工過程中,涉及到很多專業(yè)施工隊(duì)伍的協(xié)調(diào)和配合。施工管理人員要在技術(shù)層面上嚴(yán)格把關(guān),制定詳細(xì)的施工計(jì)劃,加強(qiáng)管理,提高施工技術(shù)。施工人員還應(yīng)根據(jù)工程的自身特點(diǎn),對(duì)施工中的每一個(gè)環(huán)節(jié)都要實(shí)施有效地動(dòng)態(tài)控制,認(rèn)真管理好從材料采購、施工過程到工程驗(yàn)收的全過程,并且建立良好的質(zhì)量監(jiān)督體系,提高電氣工程的施工效率,保證工程安裝質(zhì)量。
參考文獻(xiàn):
【1】武美英. 建筑電氣安裝施工技術(shù)及質(zhì)量控制【J】.科技信息,2010(30)
【2】朱普芳.建筑電氣安裝施工工藝論析【J】.中華民居,2011(2).
【3】鄭梧. 關(guān)于建筑電氣安裝施工技術(shù)及質(zhì)量控制的探討【J】.商品與質(zhì)量:學(xué)術(shù)觀察,2011(10)
【4】才越.淺析建筑電氣安裝的施工技術(shù)【J】.中國房地產(chǎn)業(yè),2011(2).
【5】GB T20299建筑及居住區(qū)數(shù)字化技術(shù)應(yīng)用【S】. 2006
關(guān)鍵詞:電氣安裝;工程質(zhì)量;預(yù)控措施
電氣安裝工程是建筑安裝工程的分部工程,通過正確的工藝,合理的程序、把門類廣泛,價(jià)值昂貴的材料,設(shè)備,成品及半成品等按照設(shè)計(jì)要求在施工中形成質(zhì)量合格的工程產(chǎn)品。考核的電氣安裝工程質(zhì)量的主要原則為:確保安全供電和用電;考慮工程的使用年限或使用壽命,功能健全,可靠;注意裝飾效果,節(jié)約能源,方便維護(hù)和檢修。安裝工程的質(zhì)量將直接關(guān)系到企業(yè)的生產(chǎn)能力的形成,生產(chǎn)效益的發(fā)揮以及建筑的使用功能和生命財(cái)產(chǎn)的安全,因此監(jiān)督承包單位確保電氣安裝工程質(zhì)量是非常重要的。監(jiān)督的依據(jù)是設(shè)計(jì)圖紙及有關(guān)電氣安裝的文件計(jì)劃等。在施工中對(duì)質(zhì)量做到控制在前,言而有據(jù)。
1 決定電氣安裝工程質(zhì)量的三大因素為:設(shè)計(jì)、施工及材料和設(shè)備制造
首先,應(yīng)該熟悉電氣安裝工程設(shè)計(jì)圖紙及說明書,參加圖紙會(huì)審并做好紀(jì)錄,全面了解設(shè)計(jì)要求和使用要求,設(shè)計(jì)文件的組成內(nèi)容是否符合標(biāo)準(zhǔn),規(guī)范使用說明,工程數(shù)量,設(shè)備與主材是否與施工圖相符,設(shè)計(jì)文件是否有錯(cuò)誤和遺漏,室內(nèi)外設(shè)備的布置和線路路線是否符合規(guī)范規(guī)定和現(xiàn)場實(shí)際,采用新產(chǎn)品是否指明產(chǎn)品來源,加工非定型產(chǎn)品是否有足夠的份數(shù)的工廠生產(chǎn)用圖紙和其他必須資料,結(jié)合供電方案,熟悉,掌握供配電系統(tǒng)構(gòu)成及切換系統(tǒng)重要符合邏輯關(guān)系,了解相關(guān)專業(yè)的系統(tǒng)功能及負(fù)載情況。
其次,對(duì)于電氣安裝施工企業(yè)的資格審查,從事建筑電氣工程的施工企業(yè),必須持有北京供電局頒發(fā)的《供用電工程施工的許可》其資格和能力,應(yīng)與承包工程的規(guī)模和技術(shù)要求相適應(yīng),電氣安裝工程由總承包單位分包的項(xiàng)目,總包單位應(yīng)對(duì)工程全面負(fù)責(zé),從事電氣安裝工程施工的企業(yè),必須有健全的質(zhì)量保證體系及技術(shù)管理體系,對(duì)安裝質(zhì)量負(fù)責(zé),施工現(xiàn)場要明確電氣工程負(fù)責(zé)人,制定施工組織,管理措施和安全措施,施工現(xiàn)場設(shè)專門的電氣技術(shù)人員擔(dān)任技術(shù)負(fù)責(zé)人,對(duì)電氣安裝施工質(zhì)量負(fù)直接責(zé)任,施工現(xiàn)場要設(shè)專職的質(zhì)量檢查人員,堅(jiān)持三檢制度,如實(shí)填寫記錄,資料要齊全有效,同時(shí)還要了解施工企業(yè)的業(yè)績,信譽(yù)及人員素質(zhì)和構(gòu)成情況。
再次,電氣安裝工程設(shè)備,材料的認(rèn)定要規(guī)范設(shè)備的采用及器材的選擇應(yīng)按照國家現(xiàn)行的技術(shù)標(biāo)準(zhǔn)的規(guī)定,出廠證明技術(shù)合格證或質(zhì)量保證書,設(shè)備應(yīng)有銘牌及安全認(rèn)證,了解,掌握對(duì)重要設(shè)備的質(zhì)量控制,檢測手段,安裝工藝,設(shè)備及材料的運(yùn)輸,保管應(yīng)符合規(guī)范及產(chǎn)品的要求,并且要做好設(shè)備及材料的防水,防潮,防火保護(hù)及冬季保溫工作。
2 電氣安裝工程施工質(zhì)量管理要點(diǎn)
施工過程中要堅(jiān)持每道工序完成后不經(jīng)過驗(yàn)收認(rèn)可,不準(zhǔn)轉(zhuǎn)入下道工序的原則;必須按圖紙施工,對(duì)于設(shè)計(jì)變更,要及時(shí)標(biāo)注在相應(yīng)的施工圖紙上;執(zhí)行持證上崗制度,落實(shí)電氣安裝施工條件,對(duì)施工單位報(bào)來的各項(xiàng)工程及隱蔽工程報(bào)驗(yàn)單,要認(rèn)真審查,交代清楚,不得遺留到下道工序;各項(xiàng)手續(xù)以文字為憑,及時(shí)填寫日志,掌握施工動(dòng)態(tài),要監(jiān)督施工單位質(zhì)量保證體系是否健全,落實(shí)三檢(自檢,互檢,交接檢)制度,三按(按圖紙,按工藝,按標(biāo)準(zhǔn))制度執(zhí)行;對(duì)供電系統(tǒng),切換系統(tǒng)的主要設(shè)備的安裝調(diào)試,要掌握詳細(xì)的技術(shù)資料及真實(shí)情況,檢查是否滿足設(shè)計(jì)要求和施工驗(yàn)收規(guī)范要求,做好記錄,對(duì)承包單位報(bào)驗(yàn)的部位要進(jìn)行隱蔽工程的驗(yàn)收,按實(shí)際進(jìn)度及質(zhì)量情況,按期填寫進(jìn)度表,工程質(zhì)量應(yīng)符合有關(guān)技術(shù)標(biāo)準(zhǔn),設(shè)計(jì)文件及合同規(guī)定要求。
3 土建施工各階段,電氣專業(yè)要及時(shí)與其他專業(yè)相配合,加快過程和進(jìn)度,保證工程質(zhì)量
3.1 基礎(chǔ)施工階段,按圖注明的穿過基礎(chǔ)的管線位置和預(yù)留孔洞,及需要埋入基墊層的管線,接地裝置的焊接等工作。
3.2 結(jié)構(gòu)施工階段,督促電氣施工做好防雷設(shè)施及引下線的焊接,每三層設(shè)置一個(gè)均壓帶,衛(wèi)生間內(nèi)做局部等電位等接地工作,同時(shí)要檢查敷設(shè)管路隱蔽工程的施工,避免漏管現(xiàn)象的發(fā)生。
3.3 抹灰階段,檢查電氣工程的箱,盒,管卡,套管是否齊全完好,不合格的要及時(shí)更換,修理,發(fā)現(xiàn)遺漏要及時(shí)補(bǔ)救,箱,盒口要規(guī)矩平整,不允許留大喇叭口,應(yīng)與墻面一平,必須將箱,盒的封堵(用紙或其它物)保護(hù),防止污染和掉進(jìn)異物。
3.4 噴漿及其后期階段,督促噴漿人員做好接線盒,開關(guān)盒,插座盒等保護(hù),噴漿后照明燈及開關(guān)和插座面板的安裝要操作正確,保護(hù)土建成品,防止將墻面弄臟,破壞。
4 電氣施工與土建配合時(shí)必須掌握的幾條線,是保證電氣施工質(zhì)量的必要條件
4.1 軸線:通過軸線計(jì)算出管,線,箱,盒的平面位置及相互位置關(guān)系
4.2 水平線:一般為50線和1米線,電氣器具依靠此線定位
4.3 墻面線:抹灰前土建沖筋確定墻面,電氣施工應(yīng)以此標(biāo)準(zhǔn),調(diào)整各種盒及箱的位置
4.4 吊頂下皮線:精裝修時(shí),吊頂下皮線是調(diào)整安裝嵌入或燈具及接線開關(guān),接線盒位置的基準(zhǔn)
4.5 隔墻線及門中線:以此為依據(jù)確定燈具,開關(guān)的位置
綜上所述:只有做到工程質(zhì)量高標(biāo)準(zhǔn),嚴(yán)要求,合理預(yù)控,才能避免電氣安裝工程的質(zhì)量通病,保障電氣安裝工程的質(zhì)量達(dá)到規(guī)范的要求。
參考文獻(xiàn)
[1] 李娜.淺談建筑電氣安裝中存在的問題及預(yù)防措施[J].中國科技信息.2009,16.
[2] 李鴻峰,傅饒.對(duì)建筑電氣工程質(zhì)量及安裝工程存在的質(zhì)量問題探討[J].黑龍江科技信息.2011,18.
關(guān)鍵詞:建筑施工;電氣安裝;質(zhì)量管理
Abstract: The increasing demand for building intelligent, will inevitably lead to an increasingly complex system of electrical equipment, give the installation and construction of a higher update request. This paper mainly discusses the installation technology of electrical engineering construction.Key words: construction; electrical installation; quality management
中圖分類號(hào):S972.7+4 文獻(xiàn)標(biāo)識(shí)碼: A 文章編號(hào):
電氣施工質(zhì)量規(guī)范較多,施工及監(jiān)控人員要結(jié)合工程實(shí)際,邊干邊學(xué),牢記規(guī)范。在工作中,一定要有強(qiáng)烈的事業(yè)心和責(zé)任感,仔細(xì)認(rèn)真,不怕麻煩,深入現(xiàn)場,與土建工程密切配合,始終把材料設(shè)備質(zhì)量的監(jiān)控貫穿于工程建設(shè)的全過程,嚴(yán)禁偽劣產(chǎn)品用于工程,嚴(yán)格質(zhì)量管理,才能保證工程按期完成,保證電氣施工工程的安全可靠,保證建筑整體運(yùn)行的先進(jìn)性和穩(wěn)定性。
一、主要設(shè)備安裝(一)遠(yuǎn)程處理機(jī)的安裝樓宇自動(dòng)控制系統(tǒng)與各可重構(gòu)處理單元RPU之間的通信是透明的,可利用同一線路不同的RPU完成同一個(gè)控制系統(tǒng)。一般而言,建筑電氣設(shè)備自動(dòng)化系統(tǒng)大量監(jiān)控的是空調(diào)機(jī)組,所以將RPU布置在機(jī)房之中或附近,把空調(diào)機(jī)組控制系統(tǒng)使用后剩余的輸入輸出接口用于連接附近的水流量計(jì)、水位信號(hào)、照明控制等。為了日后的發(fā)展,RPU的接口要留出20%~30%為宜。(二)建筑電氣設(shè)備自動(dòng)化系統(tǒng)的布線在建筑電氣設(shè)備自動(dòng)化系統(tǒng)進(jìn)行布線時(shí),要注意某些線路需要專門的導(dǎo)線,如通信線路、溫度濕度傳感器線路、水位浮子開關(guān)線路、流量計(jì)線路等,它們一般需要屏蔽線,或者由制造商提供專門的導(dǎo)線。電源線與信號(hào)、控制電纜應(yīng)分槽、分管敷設(shè);數(shù)據(jù)顯示通道(DDC)、計(jì)算機(jī)、網(wǎng)絡(luò)控制器、網(wǎng)關(guān)等電子設(shè)備的工作接地應(yīng)連在其他弱電工程共用的單獨(dú)的接地干線上。智能建筑中安裝有大量的電子設(shè)備,這些設(shè)備分屬于不同的系統(tǒng),由于這些設(shè)備工作頻率、抗干擾能力和功能等都不相同,對(duì)接地的要求也不同。(三)輸入設(shè)備的安裝輸入設(shè)備應(yīng)安裝在能正確反映其性能的位置,便于調(diào)試和維護(hù)的地方。不同類型的傳感器應(yīng)按設(shè)計(jì)、產(chǎn)品的要求和現(xiàn)場實(shí)際情況確定其位置:水管型溫度傳感器、蒸汽壓力傳感器、水流開關(guān)、水管流量計(jì)不宜安裝在管道焊縫及其邊緣上開孔焊接;風(fēng)管型濕度傳感器、室內(nèi)溫度傳感器、風(fēng)汽壓力傳感器、空氣質(zhì)量傳感器應(yīng)避開蒸汽放空口及出風(fēng)口處;(是不是少字?)管型溫度傳感器、水管型壓力傳感器、蒸汽壓力傳感器、水流開關(guān)的安裝應(yīng)與工藝管道安裝同時(shí)進(jìn)行;風(fēng)管壓力、溫度、濕度、空氣質(zhì)量、空氣速度、壓差開關(guān)的安裝應(yīng)在風(fēng)管保溫完成后進(jìn)行。(四)輸出設(shè)備的安裝風(fēng)閥箭頭、電動(dòng)閥門的箭頭應(yīng)與風(fēng)門、電動(dòng)閥門的開閉和水流方向一致;安裝前宜進(jìn)行模擬動(dòng)作;電動(dòng)閥門的口徑與管道口徑不一致時(shí),應(yīng)采取漸縮管件,但閥門口徑一般不應(yīng)低于管道口徑二個(gè)檔次,并應(yīng)經(jīng)計(jì)算確定滿足設(shè)計(jì)要求;電動(dòng)與電磁調(diào)節(jié)閥一般安裝在回水管上。(五)其它設(shè)備的安裝建筑電氣設(shè)備自動(dòng)化系統(tǒng)的監(jiān)控是由電腦按照編制好的程序進(jìn)行的,設(shè)計(jì)工程大大簡化,不需要各種設(shè)備的電氣聯(lián)鎖控制調(diào)節(jié)原理圖等,只需要簡單的監(jiān)控原理圖就可以滿足要求。但設(shè)計(jì)人員必須編制較為詳細(xì)的監(jiān)控說明軟件,還要向制造商提供各測量元件、控制器使用的條件清單(如管道規(guī)格、流體名稱、壓力、溫度、流量等),以便制造商選用各種元件規(guī)格。安裝人員根據(jù)圖紙及提供的主要元件的規(guī)格和數(shù)量進(jìn)行組裝。
二、安裝要求由于電氣工程專業(yè)性強(qiáng),在工程時(shí)間緊、作業(yè)面寬、工程繁雜、質(zhì)量要求高的情況下,若不分輕重緩急,勢必造成人、財(cái)、物的浪費(fèi)。在管理過程中,應(yīng)認(rèn)真學(xué)習(xí),因地制宜,總結(jié)經(jīng)驗(yàn),分析工程實(shí)際情況,抓住工程中的關(guān)鍵環(huán)節(jié),處理解決關(guān)鍵性質(zhì)量問題。(一)配電裝置的安裝要求配電裝置是電氣工程的核,它如同人的心臟,一旦出了毛病,人員和設(shè)備就無法正常工作,造成供電可靠性下降。為此,對(duì)配電裝置從設(shè)備進(jìn)貨到安裝調(diào)試,者隈毫不放松,嚴(yán)格按圖施工和按標(biāo)準(zhǔn)、規(guī)范驗(yàn)收。大樓內(nèi)變壓器、高壓開關(guān)柜、低壓開關(guān)柜等設(shè)備都比較先進(jìn),其生產(chǎn)廠家一般較具規(guī)模,按常理是不會(huì)出現(xiàn)技術(shù)問題。但是,在實(shí)際工程施工中,認(rèn)真檢查,常常會(huì)發(fā)現(xiàn)低壓開關(guān)柜內(nèi)回路開關(guān)與設(shè)計(jì)不符、供貨的開關(guān)大小滿足不了要求等現(xiàn)象,造成人員和設(shè)備的安全事故。在質(zhì)量管理過程中應(yīng)仔細(xì)檢查,核對(duì)圖紙,消除事故隱患。(二)電力電纜的安裝要求電纜是輸送電能的載體,若質(zhì)量不高,就會(huì)造成火災(zāi)等事故的頻繁發(fā)生。工程中使用的電纜絕大多數(shù)是沿豎井、橋架和溝道鋪設(shè),電纜集中、數(shù)量多,規(guī)格4mm2~240mm2的三芯至五芯電力電纜不等,如不嚴(yán)格審查,就會(huì)出現(xiàn)施工混亂、電纜型號(hào)錯(cuò)誤,造成運(yùn)行中電纜過熱、發(fā)生安全事故。(三)配電箱的安裝要求配電箱是電力負(fù)荷的現(xiàn)場直接控制器。要使電氣工程中的動(dòng)力、照明負(fù)荷能正常工作,配電箱內(nèi)元器件的工作性能至關(guān)重要。工程中配電箱元器件型號(hào)復(fù)雜、數(shù)量多,部分配電箱包含樓宇、消防等弱電專業(yè)的設(shè)備,電氣系統(tǒng)涉及各個(gè)專業(yè)且各專業(yè)又有自己的特點(diǎn),在設(shè)計(jì)中受各專業(yè)干擾的情況較多,造成設(shè)計(jì)修改增加,配電箱內(nèi)的設(shè)備和回路修改多。若施工單位在訂貨時(shí)只按施工圖訂貨而忽視修改,在安裝時(shí)只顧設(shè)備安裝而不仔細(xì)進(jìn)行技術(shù)審核,就滿足不了有關(guān)專業(yè)功能的要求。施工單位應(yīng)對(duì)現(xiàn)場的配電箱按設(shè)計(jì)修改通知單逐一核對(duì),糾正開關(guān)容量偏大或偏小、回路數(shù)不夠的錯(cuò)誤。電氣設(shè)備的上下級(jí)容量配合是相當(dāng)嚴(yán)格的,若不符合技術(shù)要求,勢必造成系統(tǒng)運(yùn)行不穩(wěn)定、供電可靠性差,埋下事故的隱患。
三、嚴(yán)格質(zhì)量管理電氣施工安裝中,管理人員只有努力提高自身的素質(zhì)和專業(yè)能力,才能做好質(zhì)量的監(jiān)控。(一)認(rèn)真閱圖是做好質(zhì)量管理的前提圖紙是施工的前提和依據(jù),只有詳細(xì)核對(duì)圖紙,對(duì)工程中各系統(tǒng)做到心中有數(shù),才能發(fā)現(xiàn)問題和糾正錯(cuò)誤,做到對(duì)工程質(zhì)量的預(yù)控。電氣工程系統(tǒng)設(shè)備先進(jìn)、管線繁瑣,在電氣施工前的各階段,都要仔細(xì)地審圖和校圖,特別是對(duì)每一份設(shè)計(jì)修改通知單,都要認(rèn)真核對(duì),逐一描繪到藍(lán)圖上。只有這樣地修改藍(lán)圖,監(jiān)控工程質(zhì)量,才能糾正錯(cuò)誤,保證電氣系統(tǒng)的安全、可靠。(二)熟悉規(guī)范,嚴(yán)格質(zhì)量管理電氣施工質(zhì)量規(guī)范條框較多,質(zhì)量管理人員要結(jié)合衛(wèi)隉實(shí)際,一邊施工一邊學(xué)標(biāo)準(zhǔn),不斷積累,牢記規(guī)范條例。在工作中,一定要有強(qiáng)烈的事業(yè)心、責(zé)任感,仔細(xì)認(rèn)真,不怕麻煩,深入現(xiàn)場,嚴(yán)格質(zhì)量管理。材料的質(zhì)量是施工質(zhì)量好壞的關(guān)鍵,要始終把材料質(zhì)量的管理貫穿于工程建設(shè)的全過程。只有嚴(yán)禁偽劣產(chǎn)品用于工程,才能保證電氣施工的工程質(zhì)量。(三)實(shí)現(xiàn)質(zhì)量目標(biāo)的預(yù)控質(zhì)量目標(biāo)是優(yōu)質(zhì)工程,如何具體來實(shí)現(xiàn)呢?我們認(rèn)為:甲方、監(jiān)理、施工管理人員首先必須分清工程中的重點(diǎn)環(huán)節(jié),在電氣工程施工質(zhì)量管理中,應(yīng)明確關(guān)鍵,制訂措施,根據(jù)規(guī)范對(duì)工程質(zhì)量預(yù)控。其次,監(jiān)控好重點(diǎn)環(huán)節(jié)但也不能放松其它環(huán)節(jié)的控制,這樣才能達(dá)到對(duì)整個(gè)系統(tǒng)工程的質(zhì)量監(jiān)控。電氣工程除了材料的自身質(zhì)量保證外,也要保證系統(tǒng)的功能。在知識(shí)經(jīng)濟(jì)、信息技術(shù)高度發(fā)展的時(shí)代,先進(jìn)的設(shè)備不斷出現(xiàn),功能不斷增強(qiáng),而同一產(chǎn)品,功能的差異往往造成價(jià)格的明顯不同。所以,在質(zhì)量管理中,一定要根據(jù)合同仔細(xì)推敲,嚴(yán)格管理,實(shí)現(xiàn)系統(tǒng)應(yīng)具備的功能。
關(guān)鍵詞:電氣安裝;工程質(zhì)量;預(yù)控措施
電氣安裝工程是建筑安裝工程的分部工程,通過正確的工藝,合理的程序、把門類廣泛,價(jià)值昂貴的材料,設(shè)備,成品及半成品等按照設(shè)計(jì)要求在施工中形成質(zhì)量合格的工程產(chǎn)品。考核的電氣安裝工程質(zhì)量的主要原則為:確保安全供電和用電;考慮工程的使用年限或使用壽命,功能健全,可靠;注意裝飾效果,節(jié)約能源,方便維護(hù)和檢修。安裝工程的質(zhì)量將直接關(guān)系到企業(yè)的生產(chǎn)能力的形成,生產(chǎn)效益的發(fā)揮以及建筑的使用功能和生命財(cái)產(chǎn)的安全,因此監(jiān)督承包單位確保電氣安裝工程質(zhì)量是非常重要的。監(jiān)督的依據(jù)是設(shè)計(jì)圖紙及有關(guān)電氣安裝的文件計(jì)劃等。在施工中對(duì)質(zhì)量做到控制在前,言而有據(jù)。
1 決定電氣安裝工程質(zhì)量的三大因素為:設(shè)計(jì)、施工及材料和設(shè)備制造
首先,應(yīng)該熟悉電氣安裝工程設(shè)計(jì)圖紙及說明書,參加圖紙會(huì)審并做好紀(jì)錄,全面了解設(shè)計(jì)要求和使用要求,設(shè)計(jì)文件的組成內(nèi)容是否符合標(biāo)準(zhǔn),規(guī)范使用說明,工程數(shù)量,設(shè)備與主材是否與施工圖相符,設(shè)計(jì)文件是否有錯(cuò)誤和遺漏,室內(nèi)外設(shè)備的布置和線路路線是否符合規(guī)范規(guī)定和現(xiàn)場實(shí)際,采用新產(chǎn)品是否指明產(chǎn)品來源,加工非定型產(chǎn)品是否有足夠的份數(shù)的工廠生產(chǎn)用圖紙和其他必須資料,結(jié)合供電方案,熟悉,掌握供配電系統(tǒng)構(gòu)成及切換系統(tǒng)重要符合邏輯關(guān)系,了解相關(guān)專業(yè)的系統(tǒng)功能及負(fù)載情況。
其次,對(duì)于電氣安裝施工企業(yè)的資格審查,從事建筑電氣工程的施工企業(yè),必須持有北京供電局頒發(fā)的《供用電工程施工的許可》其資格和能力,應(yīng)與承包工程的規(guī)模和技術(shù)要求相適應(yīng),電氣安裝工程由總承包單位分包的項(xiàng)目,總包單位應(yīng)對(duì)工程全面負(fù)責(zé),從事電氣安裝工程施工的企業(yè),必須有健全的質(zhì)量保證體系及技術(shù)管理體系,對(duì)安裝質(zhì)量負(fù)責(zé),施工現(xiàn)場要明確電氣工程負(fù)責(zé)人,制定施工組織,管理措施和安全措施,施工現(xiàn)場設(shè)專門的電氣技術(shù)人員擔(dān)任技術(shù)負(fù)責(zé)人,對(duì)電氣安裝施工質(zhì)量負(fù)直接責(zé)任,施工現(xiàn)場要設(shè)專職的質(zhì)量檢查人員,堅(jiān)持三檢制度,如實(shí)填寫記錄,資料要齊全有效,同時(shí)還要了解施工企業(yè)的業(yè)績,信譽(yù)及人員素質(zhì)和構(gòu)成情況。
再次,電氣安裝工程設(shè)備,材料的認(rèn)定要規(guī)范設(shè)備的采用及器材的選擇應(yīng)按照國家現(xiàn)行的技術(shù)標(biāo)準(zhǔn)的規(guī)定,出廠證明技術(shù)合格證或質(zhì)量保證書,設(shè)備應(yīng)有銘牌及安全認(rèn)證,了解,掌握對(duì)重要設(shè)備的質(zhì)量控制,檢測手段,安裝工藝,設(shè)備及材料的運(yùn)輸,保管應(yīng)符合規(guī)范及產(chǎn)品的要求,并且要做好設(shè)備及材料的防水,防潮,防火保護(hù)及冬季保溫工作。
2 電氣安裝工程施工質(zhì)量管理要點(diǎn)
施工過程中要堅(jiān)持每道工序完成后不經(jīng)過驗(yàn)收認(rèn)可,不準(zhǔn)轉(zhuǎn)入下道工序的原則;必須按圖紙施工,對(duì)于設(shè)計(jì)變更,要及時(shí)標(biāo)注在相應(yīng)的施工圖紙上;執(zhí)行持證上崗制度,落實(shí)電氣安裝施工條件,對(duì)施工單位報(bào)來的各項(xiàng)工程及隱蔽工程報(bào)驗(yàn)單,要認(rèn)真審查,交代清楚,不得遺留到下道工序;各項(xiàng)手續(xù)以文字為憑,及時(shí)填寫日志,掌握施工動(dòng)態(tài),要監(jiān)督施工單位質(zhì)量保證體系是否健全,落實(shí)三檢(自檢,互檢,交接檢)制度,三按(按圖紙,按工藝,按標(biāo)準(zhǔn))制度執(zhí)行;對(duì)供電系統(tǒng),切換系統(tǒng)的主要設(shè)備的安裝調(diào)試,要掌握詳細(xì)的技術(shù)資料及真實(shí)情況,檢查是否滿足設(shè)計(jì)要求和施工驗(yàn)收規(guī)范要求,做好記錄,對(duì)承包單位報(bào)驗(yàn)的部位要進(jìn)行隱蔽工程的驗(yàn)收,按實(shí)際進(jìn)度及質(zhì)量情況,按期填寫進(jìn)度表,工程質(zhì)量應(yīng)符合有關(guān)技術(shù)標(biāo)準(zhǔn),設(shè)計(jì)文件及合同規(guī)定要求。
3 土建施工各階段,電氣專業(yè)要及時(shí)與其他專業(yè)相配合,加快過程和進(jìn)度,保證工程質(zhì)量
3.1 基礎(chǔ)施工階段,按圖注明的穿過基礎(chǔ)的管線位置和預(yù)留孔洞,及需要埋入基墊層的管線,接地裝置的焊接等工作。
3.2 結(jié)構(gòu)施工階段,督促電氣施工做好防雷設(shè)施及引下線的焊接,每三層設(shè)置一個(gè)均壓帶,衛(wèi)生間內(nèi)做局部等電位等接地工作,同時(shí)要檢查敷設(shè)管路隱蔽工程的施工,避免漏管現(xiàn)象的發(fā)生。
3.3 抹灰階段,檢查電氣工程的箱,盒,管卡,套管是否齊全完好,不合格的要及時(shí)更換,修理,發(fā)現(xiàn)遺漏要及時(shí)補(bǔ)救,箱,盒口要規(guī)矩平整,不允許留大喇叭口,應(yīng)與墻面一平,必須將箱,盒的封堵(用紙或其它物)保護(hù),防止污染和掉進(jìn)異物。
3.4 噴漿及其后期階段,督促噴漿人員做好接線盒,開關(guān)盒,插座盒等保護(hù),噴漿后照明燈及開關(guān)和插座面板的安裝要操作正確,保護(hù)土建成品,防止將墻面弄臟,破壞。
4 電氣施工與土建配合時(shí)必須掌握的幾條線,是保證電氣施工質(zhì)量的必要條件
4.1 軸線:通過軸線計(jì)算出管,線,箱,盒的平面位置及相互位置關(guān)系
4.2 水平線:一般為50線和1米線,電氣器具依靠此線定位
4.3 墻面線:抹灰前土建沖筋確定墻面,電氣施工應(yīng)以此標(biāo)準(zhǔn),調(diào)整各種盒及箱的位置
4.4 吊頂下皮線:精裝修時(shí),吊頂下皮線是調(diào)整安裝嵌入或燈具及接線開關(guān),接線盒位置的基準(zhǔn)
4.5 隔墻線及門中線:以此為依據(jù)確定燈具,開關(guān)的位置
綜上所述:只有做到工程質(zhì)量高標(biāo)準(zhǔn),嚴(yán)要求,合理預(yù)控,才能避免電氣安裝工程的質(zhì)量通病,保障電氣安裝工程的質(zhì)量達(dá)到規(guī)范的要求。
參考文獻(xiàn)
[1] 李娜.淺談建筑電氣安裝中存在的問題及預(yù)防措施[J].中國科技信息.2009,16.
[2] 李鴻峰,傅饒.對(duì)建筑電氣工程質(zhì)量及安裝工程存在的質(zhì)量問題探討[J].黑龍江科技信息.2011,18.
關(guān)鍵詞:供水廠;機(jī)電施工;質(zhì)量問題;應(yīng)對(duì)措施
近年來,隨著科技的進(jìn)步,供水行業(yè)飛速發(fā)展,機(jī)電設(shè)備在供水工程中所占的比例越來越高,進(jìn)而使人們對(duì)供水廠機(jī)電設(shè)備安裝的質(zhì)量要求也越來越高。機(jī)電設(shè)備的施工質(zhì)量,不僅影響企業(yè)的發(fā)展,更是涉及國計(jì)民生之大事,因此,對(duì)供水廠機(jī)電設(shè)備的質(zhì)量要求越來越高,管理更加嚴(yán)格。
1供水機(jī)電設(shè)備安裝質(zhì)量管理中存在的問題
1.1機(jī)電管理及施工人員素質(zhì)良莠不齊。對(duì)于很多施工單位來說,,機(jī)電施工隊(duì)伍的整體素質(zhì)良莠不齊是一個(gè)普遍存在的現(xiàn)象,在管理隊(duì)伍中,不妄有一些業(yè)務(wù)精通,管理經(jīng)驗(yàn)豐富的人員,并且對(duì)工作認(rèn)真負(fù)責(zé),能夠從全局上把握和控制工作。但是也有一些文化素質(zhì)較低,管理水平不高的管理人員,這些管理人員主要依靠自己平時(shí)積累的經(jīng)驗(yàn)和教訓(xùn),對(duì)管理工作缺乏系統(tǒng)的學(xué)習(xí)和認(rèn)識(shí),面對(duì)千變?nèi)f化的管理問題顯得很吃力,不能統(tǒng)籌整個(gè)機(jī)電施工管理工作。同時(shí),施工作業(yè)人員也存在無證上崗、經(jīng)驗(yàn)不足等現(xiàn)象,由于這些原因的存在,會(huì)出現(xiàn)管理制度執(zhí)行不當(dāng),違章野蠻作業(yè)等情況,以上都是對(duì)機(jī)電施工質(zhì)量造成不同程度的影響。1.2對(duì)機(jī)電施工規(guī)范的重要性認(rèn)識(shí)不足。規(guī)范是國家對(duì)相關(guān)行業(yè)制定的強(qiáng)制性標(biāo)準(zhǔn),是考核機(jī)電施工是否合格的唯一標(biāo)準(zhǔn)。如果不能按照施工規(guī)范嚴(yán)格施工,那么就會(huì)在施工中遇到各種不可預(yù)估的質(zhì)量問題,而這些為題沒有得到及時(shí)處理的話,會(huì)造成不同程度的施工質(zhì)量問題,甚至?xí)绊懻麄€(gè)建筑乃至行業(yè)的發(fā)展。1.3。供水廠機(jī)電設(shè)備在施工中質(zhì)量問題比較多質(zhì)量問題歷來是供水行業(yè)的主要問題,隨著城市的發(fā)展,供水量也在不斷的增加,現(xiàn)代化水廠應(yīng)運(yùn)而生。精密機(jī)電設(shè)備在供水廠中的應(yīng)用也越來越多,這就要求在機(jī)電施工過程中要嚴(yán)格控制施工質(zhì)量,只有這樣才能保證設(shè)備能夠平穩(wěn)、經(jīng)濟(jì)、連續(xù)運(yùn)行。然而在實(shí)際施工過程中,難免會(huì)出現(xiàn)一些施工質(zhì)量問題,如:有的施工單位為了趕進(jìn)度,在設(shè)備基礎(chǔ)未達(dá)到規(guī)定強(qiáng)度時(shí)安裝設(shè)備,一些機(jī)泵設(shè)備的連接不同心,導(dǎo)致設(shè)備運(yùn)行異響與磨損,以及導(dǎo)線的規(guī)格與材質(zhì)選取不當(dāng),未嚴(yán)格按照規(guī)范進(jìn)行安裝等等,從而致使電氣連接與工藝不符合要求,整體安裝不合格,機(jī)電設(shè)備故障時(shí)有發(fā)生。1.4未能建立機(jī)電施工質(zhì)量控制體系。有的施工單位,未建立質(zhì)量控制體系或未按照質(zhì)量控制體系的要求去施工,從而造成控制措施不力,施工秩序混亂,管理不到位等情況。不僅施工質(zhì)量無法得到保障,同時(shí)浪費(fèi)人力物力,影響工序銜接、工藝的正常運(yùn)行,難以達(dá)到預(yù)想的效果。
2供水機(jī)電質(zhì)量管理的措施分析
2.1提供供水廠機(jī)電管理及施工人員的整體素質(zhì)對(duì)提高供水。廠的機(jī)電質(zhì)量管理工作具有非常重要的意義,只有人員的質(zhì)量意識(shí)和業(yè)務(wù)水平提高了,才能更好的保證機(jī)電施工的質(zhì)量所以對(duì)于機(jī)電施工的管理人員來說,不但要求具有較高的專業(yè)技術(shù)能力和水平,同時(shí)要具有先進(jìn)的管理經(jīng)驗(yàn)。隨著大量先進(jìn)而精密的設(shè)備運(yùn)用于供水企業(yè),對(duì)于管理人員的選擇,相對(duì)一般的選擇標(biāo)準(zhǔn)而言,更要高標(biāo)準(zhǔn),除了具有較高的技術(shù)水平和管理經(jīng)驗(yàn),還要具有良好的組織協(xié)調(diào)與溝通能力。并嚴(yán)格按照施工方案或作業(yè)指導(dǎo)書進(jìn)行施工,只有管理人員及施工人員的整體素質(zhì)提高了,機(jī)電施工的質(zhì)量才可以得到保證。2.2加強(qiáng)機(jī)電施工規(guī)范的管理。規(guī)范貫穿勘察、設(shè)計(jì)、施工及驗(yàn)收的全過程,是施工作業(yè)的根本依據(jù),同時(shí)也是質(zhì)量保障的前提和基礎(chǔ)。機(jī)電管理和施工人員在上崗作業(yè)前,應(yīng)進(jìn)行規(guī)范的學(xué)習(xí)和培訓(xùn)。其次實(shí)行以點(diǎn)帶面,點(diǎn)就是抓施工質(zhì)量的薄弱環(huán)節(jié),再從各個(gè)方面進(jìn)行全面規(guī)范化管理,提高供水廠的機(jī)電施工管理。2.3加強(qiáng)機(jī)電施工的質(zhì)量管理,降低質(zhì)量隱患。機(jī)電施工管理是指在施工過程中,管理和施工人員等各方關(guān)于質(zhì)量的相互協(xié)調(diào)的活動(dòng),是圍繞著使機(jī)電安裝滿足質(zhì)量要求,而開展的一系列的管理活動(dòng)。以下主要從影響質(zhì)量的幾個(gè)重要因素和實(shí)行質(zhì)量“三檢制”加強(qiáng)質(zhì)量管理,降低安全隱患。2.3.1加強(qiáng)影響機(jī)電施工質(zhì)量因素的管理。(1)機(jī)電施工管理及施工人員的素質(zhì)和技術(shù)操作水平,必須經(jīng)過嚴(yán)格的考核和評(píng)估,使其質(zhì)量意識(shí)和組織管理能力能夠滿足質(zhì)量要求。(2)合理選擇施工機(jī)械,確保機(jī)電施工質(zhì)量。對(duì)施工所用的機(jī)械設(shè)備應(yīng)根據(jù)工程需要從選型、性能、參數(shù)及使用操作要求等方面加以控制,符合安全,經(jīng)濟(jì),適用,環(huán)保等方面的要求。(3)施工工藝的先進(jìn)合理是直接影響工程質(zhì)量的關(guān)鍵因素,因此,必須結(jié)合實(shí)際,綜合考慮,制定和采用技術(shù)先進(jìn),經(jīng)濟(jì)合理,安全可靠的施工技術(shù)方案。2.3.2實(shí)行施工質(zhì)量“三檢制”。嚴(yán)格落實(shí)質(zhì)量檢驗(yàn)制度。實(shí)行操作者和質(zhì)檢員相結(jié)合的“三檢”管理制度,即自檢:施工班組人員在施工過程中,按照標(biāo)準(zhǔn)規(guī)范要求進(jìn)行的自我檢查制度,經(jīng)自檢合格方可繼續(xù)施工?;z:工序之間施工完畢后互相檢查。專檢:即專職質(zhì)檢員的質(zhì)量檢驗(yàn)評(píng)定,未經(jīng)專檢合格的項(xiàng)目不得繼續(xù)施工。所以,為保證機(jī)電施工質(zhì)量,必須嚴(yán)格落實(shí)“三檢”制度,層層把關(guān)。2.4建立質(zhì)量控制體系,實(shí)現(xiàn)質(zhì)量目標(biāo)的控制。為確保機(jī)電施工有效的進(jìn)行,進(jìn)行系統(tǒng)而全面的質(zhì)量控制,必須建立質(zhì)量控制體系及運(yùn)行機(jī)制,實(shí)施質(zhì)量目標(biāo)的控制。不斷尋求改進(jìn)機(jī)會(huì)、研究改進(jìn)措施,保證機(jī)電施工質(zhì)量控制系統(tǒng)的不斷完善和持續(xù)改進(jìn),不斷提高質(zhì)量控制能力和控制水平。
3結(jié)語
隨著機(jī)電一體化的發(fā)展,機(jī)電工程在供水廠的應(yīng)用越來越廣泛,設(shè)計(jì)的專業(yè)和領(lǐng)域也越來越多,技術(shù)更新更快,更復(fù)雜。所以在供水廠的機(jī)電施工中,質(zhì)量管理非常重要,施工質(zhì)量管理中,在明確質(zhì)量目標(biāo)的前提下,貫徹執(zhí)行建設(shè)工程法規(guī)和標(biāo)準(zhǔn),正確配置施工生產(chǎn)要素和采用科學(xué)的管理方法,完善質(zhì)量保證體系,只有這樣,才能保證機(jī)電施工質(zhì)量,才能保證機(jī)電設(shè)備安全有效運(yùn)行。
作者:楊小征 單位:唐山市自來水公司